Sheds and approvals

Do you need approval for a shed in Canberra?

What you can build without a DA, what still needs a certifier, and why the answer changes the moment you cross into NSW.

Fig. 02Block plan building line, 1.5 m strips, solar envelope
Short answerUpdated

In the ACT, a shed can skip development approval if it meets the exempt rules: it fits your block's size limit (10, 25 or 50 m² depending on block size), stays no higher than 3 m, sits behind the building line and inside the solar envelope. It may still need building approval from a certifier. In NSW, a garden shed can be exempt if it's no bigger than 20 m² in a residential zone (50 m² in some rural zones) and no higher than 3 m. Anything bigger needs a CDC or a DA.

The quick version

  • In the ACT, how big your shed can be without a DA depends on how big your block is.
  • "No DA needed" isn't the same as "no approval needed". Many ACT sheds still need building approval.
  • Over the border in Queanbeyan, Googong or Yass, the NSW rules apply, and they're quite different.
  • Garages, workshops and commercial sheds are usually too big for the exempt path.

ACT: how big can a shed be without a DA?

The ACT's exempt rules for enclosed sheds and garages are in section 1.42 of the Planning (Exempt Development) Regulation 2023. The biggest surprise for most people is that the size limit depends on the size of your block.

Your block sizeBiggest exempt shed
Under 500 m²10 m²
500 m² to under 600 m²25 m²
600 m² or more50 m²

Plan area of the shed. Source: Planning (Exempt Development) Regulation 2023 (ACT), schedule 1, section 1.42.

There is no flat 20 m² rule in the ACT. On a block under 500 m², an exempt shed tops out at 10 m². On 600 m² or more, it can be 50 m².ACT Planning (Exempt Development) Regulation 2023, s 1.42

ACT: the other rules your shed has to meet

Size is only one test. To be exempt from a DA, an enclosed shed or garage also has to tick all of these:

  • Height: no more than 3 m above natural ground level. It can go up to 4 m if no part of it rises above a 30° line drawn from 3 m high at the boundary.
  • Solar envelope: no part of the shed can stick out past your block's solar building envelope, which protects your neighbours' winter sun.
  • Behind the building line: the shed has to sit behind the front building line. If it's bigger than 10 m², it also has to be at least 15 m back from the front boundary.
  • Near the side or back fence: anything within 1.5 m of a side or rear boundary has to be the only structure in that strip, or meet the extra rule for a second one, where the two together can't present more than 30 m² towards the boundary.

Carports and open-sided structures have their own section (1.43): a roof of no more than 50 m², walls on no more than two sides, behind the building line and within the same height limits.

No DA doesn't mean no approval

This is the one that catches people out. The exemption above is from development approval. The regulation itself notes that the work may still need building approval under the Building Act 2004. For most garages and decent-sized sheds, that means a private building certifier checks the plans and engineering before work starts and inspects it along the way.

The building code still applies either way. The frame has to be engineered for your site's wind rating, and the slab designed for what's going in it.

Over the border: the NSW rules

If your block is in Queanbeyan, Jerrabomberra, Googong, Bungendore, Yass or anywhere else on the NSW side, the state's Codes SEPP applies instead. Clauses 2.17 and 2.18 set the standards a garden shed must meet to be exempt, and if it meets every one, you don't need planning or building approval at all.

Residential zonesRural and R5 zones
Biggest exempt shed20 m²50 m²
Maximum height3 m3 m
Setback from boundaries900 mm5 m
PositionBehind the building lineDepends on the zone

A few more conditions apply. On bushfire-prone land, an exempt shed has to be built from non-combustible materials. Sheds can't be used as living space. And you still need council's permission to remove or prune trees, or to connect stormwater.

Bigger than that? A shed that meets the state's standard rules can go through a complying development certificate (CDC) with a private certifier, which can be approved in as little as 20 days. Anything else needs a DA through the local council, which is Queanbeyan-Palerang Regional Council or Yass Valley Council around Canberra.

The NSW figures summarise clause 2.18 of the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008. The rules are amended from time to time, so we always confirm them against the current version before you build.

Garages, workshops and commercial sheds

A double garage is usually around 36 m², and a decent workshop is often 60 to 100 m² or more. On a typical Canberra suburban block, that's beyond the exempt limits, so plan on approval from the start. Commercial and industrial sheds always go through a proper approval, and farm buildings in NSW rural zones have their own set of rules.

Know someone planning a build? Send this their way.

Side by side

The same shed, either side of the border

Say you want a 6 × 6 m double garage, 36 m², on a 650 m² suburban block.

In the ACTIn NSW
Exempt from a DA?Can be, if it's 15 m back from the front boundary and meets the height and envelope rulesNo, it's over 20 m²
Likely approvalBuilding approval through a certifierA CDC, or a DA with council
EngineeringNeeded for the wind rating and slabNeeded for the wind rating and slab
Fig. 03ACT exempt limits 10, 25 and 50 m² by block size
FAQ

Questions about shed approvals

Can I build a shed on the boundary in the ACT?

Within 1.5 m of a side or rear boundary, an exempt shed has to be the only structure in that strip, or meet the extra rule for a second structure, where the two together can't present more than 30 m² towards the boundary. It also has to stay within the height limits and the solar envelope.

Do I need approval for a carport in the ACT?

A carport can be exempt from a DA if its roof is no more than 50 m², it has walls on no more than two sides, it sits behind the building line and it's within the height limits. Building approval may still be needed.

Does an exempt shed still need engineering?

Yes. Being exempt from approval doesn't exempt the shed from the building code. It still has to be engineered for your site's wind rating, with a slab designed for what goes in it.

How long does a shed approval take?

In NSW, a CDC can be approved in as little as 20 days. ACT building approval through a certifier is usually a few weeks once the plans and engineering are ready. A DA takes longer in either place.

What happens if I build a shed without approval?

You could be asked to get approval after the fact, change the shed or take it down, and unapproved structures can cause headaches when you sell. It's far cheaper to check first.

Tell us the size and the spot. We'll sort the approval.